Our Blog On-Demand

Content


Knowledge Hub

Understanding kW vs kWh (and Meter Data) to Lower Your Utility Bills

March 31, 2017

Many customers as well as my colleagues at CPower often ask me about the benefits of installing reliable metering equipment to access energy data in near real time. I typically respond with a handful of advantages (some listed below), but even before going there I find it useful to explain the full context about why these are important.

No discussion on the topic would be complete without a basic understanding of Demand (measured in kilowatts or kW) versus Consumption (measured in kilowatt hours or kWh). This is key to making the right choices when it comes to reducing energy costs, since electricity use for a commercial/industrial customer is typically billed and metered after taking at least these factors into consideration:

  1. Maximum kilowatt use (or kW demand) during a given period, typically in 15- or 30-minute intervals, and
  2. Total cumulative consumption (in kWh).

So, what’s the big deal between kW vs kWh?

An analogy using traditional light bulbs can help: Consider a single 100W bulb lit for ten hours versus ten 100W bulbs lit simultaneously for one hour. In both scenarios, the total cumulative “consumption” is 1,000 watt-hours (or 1 kWh). In the first case, however, the single light bulb will “demand” 100W or 0.1 kW from the electric supplier. Thus, the utility must have that 0.1 kW ready whenever that bulb is switched on. But note how the second scenario impacts the utility from a “demand” perspective. The electric supplier in this case must be ready to deliver 10x as much ‘capacity’ in response to the demand of the 10 light bulbs burning simultaneously!

Quite simply, here’s the difference. If these two scenarios reflected the behavior of two different customers, and if they were each billed for only their consumption, then both would get the same bill (for 1 kWh of energy used) even though the burden placed on the utility to meet each customer’s energy requirement is very different. Among other reasons, this is primarily why C&I (as opposed to residential) customers are typically metered and billed based on both their hourly “consumption” patterns and their peak “demand” for energy.

Demand-side energy management in near real time

CPower’s savvy demand response (DR) customers effectively leverage the energy they consume as a facility asset. Our diverse customer base covers mid- to large-sized electricity users in commercial, industrial, government and institutional organizations, including water/wastewater pumping and treatment facilities, colleges and universities, public agencies, office campuses, cold storage, data centers and a wide range of manufacturing facilities, to name just a few.

Many of our most active DR participants nationwide additionally leverage real-time metering for its clear advantages, including more visibility and control over load reductions as well as better overall energy management and sustainability benefits. The image above shows just two of the many views available to users via the CPower App (the graph on top shows 7-day hourly interval consumption while the one below shows demand on an intra-day 1-minute interval chart).

Key reasons to get real-time metering installed at your facility:

  • You can identify unusual or erratic equipment behavior to help avoid catastrophic failure. This is from a recent real-world example: Our team at CPower was working with the operations team for a large commercial real estate and property management firm, and picked up on unusual/erratic daytime usage patterns at one of their facilities. A look at the major systems of the building revealed that a chiller which had been recently serviced was to blame. Further investigation revealed that during a recent service call the chiller had been severely over-charged with refrigerant. Having a near real-time window into their energy usage enabled the facilities personnel to identify the unusual usage pattern, and proactively remedy a potential chiller issue that could have resulted in thousands of dollars in repair costs and possibly escalated their demand charges had it gone unnoticed.
  • Similarly, you may discover unusual, wasteful patterns or aberrations in overall facility energy usage as well as specific areas (e.g., an BAS reset inadvertently switches on all lights in an unoccupied underground parking garage at 2 AM).
  • Simplify on-site event planning (e.g., for K-12 schools or colleges) and/or production line scheduling (for manufacturing) with day-ahead pricing and forecasting at your fingertips.
  • Quickly and accurately substantiate the impact of your energy efficiency initiatives and sustainability programs (and share results with your team and management).
  • Avoid setting a new annual or monthly consumption peak, enabling you to manage demand charges for next year. Click to see more on Peak Demand Management in New England and Texas, for example.
  • Immediately evaluate the efficacy of (and fine tune as needed) new load curtailment strategies.
  • Further leverage your building automation systems and curtailment planning while minimizing impact on occupants (students, staff, employees, tenants, etc.).
  • Facilitate optimized participation in multiple DR programs, including Emergency Capacity, Economic DR, Ancillary Services, and more.
  • In addition to monitoring real-time utility load, several customers (i.e. a manufacturer of water valves and a supplier of military components) also view sub-meter data in the CPower App to provide them with a more granular, process-level picture of the energy usage in their facility.

The Bottom line

Real-time metering ultimately increases your DR earnings and savings to fund additional efficiency initiatives, while complementing your facility’s energy conservation and sustainability efforts. There are no out-of-pocket costs, since fees to install hardware, support software provisioning and enable data measurement & verification (M&V) are typically covered by DR program earnings.

By giving you near real-time visibility and analytics of your energy consumption, enhanced metering techniques provide more earnings and savings via greater control over your DR participation and greater awareness of electricity usage patterns (remember kW vs kWh!)

Surviving New EPA Rules and the Emergency Generator Regulatory Maze

February 28, 2017

Is your organization one of the thousands of commercial/industrial energy customers that use back-up generators (BUGs)?  Are they used as emergency generators (a.k.a., EGs or gensets) in demand response (DR) programs? If so, 2016 may have felt like an episode of the “Survivor” reality show, except instead of the usual cast of GenX characters and challenges you were unfortunately tasked with surviving a maze of ever-changing genset regulations.

Bad News, Good News:  The past year saw important changes regarding the use of stationary reciprocating internal combustion engines (RICE) that continue to evolve at the federal level as administered by the U.S. Environmental Protection Agency (EPA), which itself is in now in the midst of changes with newly-confirmed administrator Scott Pruitt at the helm. EPA rules provide that BUGs that are intended for emergency use when blackouts occur are exempt from reporting requirements and most emissions regulations.  The bad news is that EPA changes significantly restricted the circumstances where such generators can be compensated for operations while the grid is still up.  The good news is many such generators can achieve “non-emergency” status without equipment upgrades by meeting specific permitting and reporting requirements.

Bit of History – 50-hour Rule No Longer Applies: In early 2016, it was determined that EGs could potentially participate in DR programs under a different rule (referred to as the “50-hour rule”).  A coalition of DR providers including CPower took specific steps to clarify the applicability of the 50-hour rule with EPA as well as explore avenues to address concerns with the prior 100-hour rule as related to EG use for DR:

  1. We funded an extensive legal review on the 50-hour rule which outlined the case for allowing EGs to continue DR participation with this rule as a basis.
  2. We shared our well-documented analysis with EPA, who responded that they were not in agreement.
  3. While we believe the EPA’s interpretation is not aligned with the actual language in the regulation nor the structure of the electricity market, federal agencies such as EPA enjoy the latitude to interpret their regulations in any manner they deem appropriate.
  4. While CPower will continue to try to convince EPA that our well-documented position bears merit, all DR service providers clearly need to comply with EPA’s current interpretation.

Further confounding the situation is that a generator classified as “nonemergency” under federal regulations could be deemed “emergency” under state and/or local regulations. Recent examples include the Rule 222 that applies to permitting in New York; while California is moving from the traditional environmental permitting approach towards utility-based restrictions.

What This Means to You: As a DR participant with EGs, you should always be aware of the nuances defining EG assets that do not meet EPA’s interpretations of local requirements as well as the Federal Non-Emergency standard for DR curtailments. This applies even if your current DR service provider may advise you otherwise (especially regarding the use of EGs via the 50-hour rule). Any reputable vendor certainly should not expose you to any potential EPA violations or penalties. And if you indeed find out that EGs are not permitted for use in DR programs, make sure your service provider has an experienced engineering team who is willing to work with you to achieve the best possible alternative curtailment strategies.

On the Positive Side: Again, the good news is that in many instances, you can still use EGs to participate in DR programs and support grid reliability. A good curtailment service provider or DR aggregator should be able to assist clients with specific steps for permitting and retrofits so their engines can still participate wherever possible. At CPower, we have helped several clients with permitting so their engines can now effectively participate in emergency DR events to support the grid. Some of these services include:

  • Helping clients evaluate generation assets for permitting compliance at both the federal and state/local levels
  • Upgrading engines with aftermarket controls and/or automated DR (ADR) controls
  • Developing recommendations for adding load to optimize use of generators
  • Facilitating engine and generator upgrades (either working with a carefully vetted partner or customer-preferred vendor)

Bottom Line: As capacity costs increase, active DR participation becomes even more compelling and relevant. Changes in EPA regulations have impacted the ability of DR customers like you to use stationary emergency generators as part of your load reduction strategies.  Luckily, you can look to DR service providers to offer valuable “survival tips” that can bring this episode to a stable ending.

“Thanks to accurate guidance from CPower’s engineering team, our engines were successfully permitted for use in demand response by the state’s Department of Environment. Their in-depth knowledge and tenacity throughout the process clearly contributed to enabling our facilities’ continued participation in the 2017 DR performance season.” – Facilities Director at a large New England based manufacturing firm.

CPower takes a leadership role and shaping market transformation while advocating for our customers to help you navigate the regulatory maze and maximize DR program benefits. The result? Increased energy savings and earnings not just from optimized participation in Emergency DR, but also in non-emergency voluntary programs (like price based Economic DR). In some cases, you can also use your engines for peak-shaving to reduce capacity costs while maintaining compliance with environmental regulations.

Do you have a generator? Does it meet State and EPA guidelines? Are you leveraging it as a demand response revenue resource? Check out our Emergency Generator Decision Tree today to ensure you make the right EG permitting and compliance choices moving forward.

Managing Rising Costs Amidst the Alphabet Soup of NY Energy Initiatives

January 30, 2017

If you’re a mid- to large-sized energy user in New York, you’ve likely come across a veritable alphabet soup of acronyms: REV, CES, DR, DER…the list goes on. Many of you who run commercial and industrial (C&I) businesses know that you can actively leverage Demand Response (DR) programs and earn revenue by curtailing load when called upon to do so during emergencies to support grid reliability. Granted, some years have been more rewarding than others since capacity prices ebb and flow in New York just like in other energy markets. Of course, capacity prices have risen substantially since 2012, resulting in increased earnings from DR participation in New York. So what can DR participants across New York expect in 2017 and beyond?

First, a bit of context on REV and CES:

In 2012, Hurricane Sandy hit the East Coast, causing devastation and leaving millions without power.  Shortly thereafter, working with the New York governor’s office, New York Power Authority and other state agencies, the Public Service Commission (PSC) launched the landmark Reforming the Energy Vision regulatory proceeding. Now commonly referred to as REV, its goal is to make the power system cleaner, resilient and more affordable. Regulators aim to transform traditional utilities into platform providers — entities that facilitate the deployment of distributed energy resources (DERs) and use them instead of traditional infrastructure.  And Demand Response is poised to continue to play a vital role as this initiative evolves.

In simplest terms, the Clean Energy Standard (CES) mandates New York to acquire 50% of its energy from clean resources by 2030. As part of this, it seeks to further that goal by providing zero-emission credits (ZEC) to support upstate nuclear plants that were in danger of closing. In late 2016, the PSC fended off numerous challenges to its adoption of the CES and its subsidy for nuclear power generators. Keep an eye on this space, however, as the PSC’s order doesn’t mean this is finalized (as of this writing in Feb 2017, two court challenges remain pending). Generators and some environmental advocates said the ZEC program — which critics say will cost over $7 billion over its 12-year lifespan — goes beyond the authority granted to the PSC by state law.

Impact on your bottom line:

In the near term at least, REV and CES, while noble causes, are going to lead to increased fixed costs (~$4/MWh) on mid- to large-sized energy consumers.  This scenario, however, also presents additional opportunities and specific actions you can take today to offset these costs:

  • Increased DR participation especially in new distribution utility programs, and
  • Capacity tag management.

New DR Programs: Both the NYISO and New York Electric Utilities offer demand response programs that pay businesses like yours for using less energy when the grid is stressed. Many commercial and industrial businesses in New York aren’t aware of the new summer-only local utility programs available to them via an authorized DR services provider. These programs offer another revenue stream in addition to the NYISO DR program that they may have been enrolled in for years. In 2016 for example, the New York Public Service Commission mandated that local utilities provide a Commercial System Relief Program (CSRP) throughout their entire service territory as part of a statewide effort to develop a new regulatory framework which includes incentives to leverage the deployment of distributed energy resources such as demand response.

Capacity Tag Management: Additionally, there are demand management services that can help significantly lower your capacity charge which make up 20-40% of the total supply portion on your monthly utility bill. The capacity charge is based on your individual capacity tag which, in New York, is determined by your facility’s usage when the NYISO sets its single annual peak hourly demand across the whole system. CPower sends an advanced day ahead demand management notification to reduce your usage when it is likely the NYISO will hit its hourly peak demand, thus reducing your capacity tag and capacity charges for the following year.

In the end, it’s all about implementing smarter techniques to manage your overall energy spend. The NYREV was launched 3+ years ago but it’s more relevant now than ever to survive as a large C&I energy user, as it will certainly change how energy is transacted in the future. At CPower, our job is to stay abreast of these developments and keep you informed about their potential impact. To get started, check out the various programs available in NY and informational videos to learn more on how you can offset rising energy costs in 2017 and beyond.

White Paper: The New England Electric Power Market

January 23, 2017

In the New England electric power market, sharply rising capacity costs and energy volatility in the New England power market will increase your electricity costs despite relatively low fuel prices and flat usage trends. This white paper explores the underlying reasons, and goes on to explain specific actions commercial and industrial customers can take to mitigate these cost increases.

ISO New England (ISO-NE) is responsible for keeping electricity flowing across the six-state New England region: Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island, and Vermont. In so doing, ISO-NE’s core mission is system reliability.

To ensure reliability ISO-NE oversees the day-to-day operation of New England’s electric power generation and transmission system to keep the energy that generators supply to the grid in near-perfect balance with consumers’ energy demand. To ensure the system maintains adequate generating and transmission capacity to serve current and future needs ISO-NE manages a comprehensive regional pwoer system planning process and the region’s competitive wholesale electricity markets.

White Paper: The Evolving New York Energy Market

In this white paper, CPower’s Mike Hourihan aims to explain how recent events have played a role in shaping both the New York Energy Market’s current state and its evolution. He’ll also attempt to predict what might be in store for the market and how he believes New York businesses can position themselves to better manage their energy today and in the future.

Energy Policy 101: How the Movement of Electrons is Regulated

December 12, 2016

Energy policy development is complicated.   Recall that the electric industry has been regulated for more than 100 years and it remains highly regulated today, even with competitive markets.  Moreover, both the Federal government and States have roles to play in regulation.  Using examples, this article focuses on federal jurisdiction over “wholesale” electricity that flows across state lines and is not sold for direct consumption to end users.  Sales to end users, including authorization of competitive retail suppliers, is the exclusive jurisdiction of the states.

In the U.S., policy at the highest level is established by Acts of Congress and the President.  It is implemented by the executive branch including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DoE).  This policy establishes a framework for the tariffs that govern the use of the nation’s electric transmission grid.  It is useful to think of this framework as a “top down” process.  The owners and operators of the transmission grid, in turn, submit tariffs that comply with the law and policy to FERC for approval.  The development of tariffs is a “bottom up” process.

Three examples of the biggest orders to come out of FERC during President Obama’s administration include FERC Order 745, which required ISOs and RTOs to pay customer-side capacity resources such as demand response an equivalent value to what power plants and other supply-side resources earn; FERC Order 755, which required ISOs to create programs to reward “fast-responding” resources such as batteries for frequency regulation; and FERC Order 1000, which has set up a new regime for transmission operators and utilities to plan for, and pay for, regional grid investments.

The FERC has been instrumental in creating Regional Transmission Operators (RTOs) through policy decisions.  RTOs and Independent System Operators (ISOs) have largely eliminated the need to set wholesale electricity prices by a fixed tariff and instead allow prices to be established by markets.  The detailed implementation of electric policy is done at the RTO level. FERC’s decisions and orders apply to the tariffs of ISOs and RTOs that run much of the U.S. power grid. About 70 percent of the country is served by ISOs and RTOs, which fall under federal jurisdiction because they cross state lines.

The shift to RTOs has not eliminated the need for regulation of electricity.  Instead it has shifted the regulatory focus from setting prices to setting market rules.  The market rules are embodied in the RTO tariffs.  The FERC is responsible for approving the RTO tariffs.  The RTO tariffs are developed with varying degrees of stakeholder input, depending on the RTO itself.  The basic process follows the steps from stakeholder consideration to RTO and final review and approval by FERC using stakeholder input as shown below:

policy-process

Each RTO handles stakeholder consideration differently. PJM Interconnection, for example, is the only RTO that is required to accept stakeholder recommendations as determined by a vote – at least on some issues.  Other RTOs simply consider the input of stakeholders and file what they think best.  There is little doubt that PJM has the most robust process. Most issues are addressed through a series of meetings that follow a set process.  The process is not unlike a government legislative body with committees, subcommittees, etc.  Often stakeholders reach consensus and many issues are resolved with no or nominal opposition.

Demand Response Policy Considerations

Perhaps one major exception to consensus pertains to issues involving capacity market design, including Demand Response (DR) participation.  On these issues, stakeholders are typically split between generation owners – including incumbent utilities – and load interests.  This is because any changes that reduce the opportunity for generation participation or revenue leads to reduced income for generators.  Such changes include enabling competitive resources such as DR and reductions in overall capacity requirements.

Conversely, stakeholders representing users of electricity oppose changes that increase costs without a credible probability of improving reliability.  As a result, most controversial issues have competing proposals.  Stakeholder votes are allocated in such a way that a required two-thirds’ supermajority (this applies to PJM) for approval of contested changes is difficult to reach.   A deadlocked stakeholder process allows PJM to file changes that may not have broad stakeholder support.  RTOs are non-profit entities without a commercial stake in market outcomes.  However, as organizations, PJM and other RTOs have an inherent bias toward “reliability” which often results in costly requirements for more resources, especially conventional generation.

Stakeholders that oppose an RTO filing have the opportunity to “protest” the tariff changes at FERC.  FERC need only determine that a filing is “just and reasonable”. While ostensibly the “just and reasonable” standard may include cost considerations, FERC, like PJM and other RTOs, also has a bias toward reliability and often will accept the RTO filing regardless of cost implications.

FERC Decisions and the Appeals Process

FERC decisions can be appealed to the federal courts on the basis non-compliance with the governing law, or an “arbitrary and capricious” decision.  Appeals Courts avoid ruling on the substance of a FERC ruling because this can place the Court in the position of creating laws and regulations.  Appeals Court decisions can be appealed to the Supreme Court as occurred in the high-profile case of FERC Order 745.  In particular, owners of conventional generation (the petitioners) opposed the Order because the treatment of demand response threatened their revenues and they took FERC to court.  The case hinged primarily on the issue of state versus federal jurisdiction (was the Order consistent with the Federal Power Act’s provisions designating retail rate setting as the exclusive jurisdiction of the states?).

In a major victory for the DR industry, the U.S. Supreme Court upheld FERC Order 745 via a 6-2 decision in January 2016, reversing a lower court opinion that found that it violated states’ jurisdiction over retail energy pricing, and dealing a blow to the utility group that brought the original lawsuit. DR providers and environmental groups supported FERC Order 745, noting that it has opened markets that have brought significant new demand-side capacity to the country’s grid operators for use in controlling the wholesale grid. Order 745 also helped reduce the need for fossil fuel-fired power and lowered overall electricity costs for consumers. But the underlying legal question behind the lawsuit — the bounds between federal and state jurisdiction over energy markets — could be modified by Acts of Congress.

You can see why the process of defining energy policy can be extremely complicated in practice. CPower takes a leadership role in shaping market transformation and regulatory reform, while working hard to maximize program benefits for our customers. It’s imperative that our Market Development team constantly stays abreast about regulatory processes as thought leaders in the DR community. These efforts enable us to provide services that take the complexity out of DR participation within the context of changing program rules, while optimizing your energy savings and earnings. This will become increasingly critical as energy markets continue to transform in the near future.

Hot Summer Ends Without Emergency Demand Response Events in PJM

October 07, 2016

The 2016 PJM summer compliance season which runs from June through September has come to an end without a PJM-initiated emergency demand response (DR) event.  The first six months of the year were already one of the warmest on record. So, for many of us sweating it out across the northeast, it was no surprise that this summer produced several heat waves that pushed system peaks to their highest levels in recent years.  PJM’s top 5 system peaks (see table), reflect the summer’s weather and should be the Five Coincidental Peaks (5CP) that drive customers’ capacity charges through their Peak Load Contribution (PLC).  It is important to note that any load reductions during these hours may reduce your capacity charges for next summer.

5cp-pjm-summer-2016

When it came to actual demand response events, however, a different picture unfolded compared to prior years. For instance, the 2013 summer saw system peaks at similar levels and was one of the most active summers for demand response customers ever.  So you may ask: Why were no Emergency DR events called this summer, despite the heat and high system peaks? A few reasons come to mind:

  1. Some of it may be attributed to PJM’s new reliability product, Capacity Performance (CP), which debuted this delivery year and imposes greater availability requirements on generation;
  2. Some of it may be attributed to increased transmission efficiency;
  3. Also, flat or declining system peaks are starting to reflect the impact of energy efficiency regulations (the last system peak demand record was set in 2007); and finally
  4. Pure Luck? After all, the timing of several heat waves passing through the PJM territory coincided during weekends.

Whatever the primary reason(s), PJM Emergency DR customers should take pride in their commitment to be on standby to reduce load when called upon. Your ability to curtail electricity consumption when needed by the grid is a tremendous asset to maintaining system reliability and preventing potential blackouts/brownouts.

This doesn’t mean that PJM may not have a reliability issue beyond the summer as the program year does run through May 2017. Also, while the summer period yields the greatest risk of an emergency event, demand response customers that have committed to curtailments all year should continue to be prepared to perform and reduce load if/when needed to support grid reliability.

Moreover, with the transition to the new CP product, demand response is morphing into a year-round program. Customers can start participating in CP now to get themselves prepared for the coming changes and earn additional capacity revenue in the process. Many forward-thinking facility managers are already thinking about how they may be able to participate beyond the summer and are reviewing effective winter curtailment strategies.

CPower would like to take this time to thank all demand response customers for their commitment to PJM reliability this summer.  CPower customers can always review their load drop test and event performance in the CPower App and should be expecting summer performance reports and payments starting early November.

Last but not least, we always encourage all participants to stay tuned for earnings opportunities in other DR programs available. Many participants augment their demand response earnings from the capacity program via active participation in PJM’s voluntary programs such as (price based) economic demand response and (faster response) ancillary services such as synchronized reserves.

Please feel free to contact Dann or the CPower team if you have any questions. Our engineering team is happy to help you understand the nuances of participating in these programs and assist in optimizing your overall energy savings and earnings year round.

Choose Your Own Curtailment Adventure: “School’s in Session”

September 02, 2016

You’re a facilities manager in the public school system. Your district of twelve schools participates in demand response programs annually. Each year, you alternate the six schools that hold summer classes, which presents you with a unique opportunity to earn money through demand response.

What do you do?

1) You register the six schools that are NOT being used for summer classes in demand response programs.

This strategy insures a guaranteed load drop, since these six campuses are not being used during the summer months when demand response events are likely to be called. This course also insures that no one will be inconvenienced since the faculty, staff, and students will be spread among the other six campuses.

Since peak load contributions (PLC) are calculated during the previous year, you’re all but assured of having a PLC near zero provided you continue to alternate the six schools used for summer classes year after year.

It’s easy money for the school district. And why not? When was the last time the power company had to hold a bake sale to raise money for the things they need but can’t afford?

Click HERE to choose the ‘Easy Money for Education’ adventure and find out what happens next.

2)  You talk to your curtailment service provider (CSP) and devise a curtailment strategy that incorporates the campuses you are using.

While potentially more of an inconvenience for staff and students (and potentially less money earned from demand response) you realize that the purpose of curtailment programs is not to game the system. Demand response exists to alleviate grid stress by reducing load when the demand for electricity outpaces supply.

Click HERE to choose the ‘Do the Right Thing’ adventure and find out what happens next.

NYISO is Ready for Summer Demand. DR Customers Should be Ready, too.

August 17, 2016

What can demand response participants expect in New York this summer? Let’s take a look at a few factors.

NYISO reports adequate summer supply, though concerns loom in Western New York…
On May 19, 2016, NYISO issued its ritual summer press release stating, “Electric supplies in New York are expected to be adequate to meet forecasted demand this summer.” However, at the time there was considerable stakeholder trepidation over potential transmission constraints in Western New York arising from the recent retirements of the Dunkirk Steam and Huntley Generation stations. There was an anecdotal sense that energy and reserves pricing in the early spring was already showing more volatility than normal.

NYISO has undertaken a number of initiatives over the past 18 months to bolster infrastructure in the region to improve transmission flows and reactive capacity. They have also implemented changes in their intraday forecasting procedures for the region to better manage congestion, in an attempt to minimize real-time pricing volatility.

How have these factors affected in the markets thus far…
The concern didn’t appear to much spill-over into the capacity market. The Rest of State Strip auction cleared at $3.62 for Summer 2016, up only 12 cents from the summer of 2015, despite the unit retirements. Spot auction prices jumped up to $5.27 in May, but have since retreated back near the Strip price at $3.64 for August. On balance, not a significant deviation from the prior year. And like the previous year, there have so far been no dispatches for Special Case Resource (SCR) customers.

In the 10-minute synchronous reserves market, the 12-month rolling average 5-minute real-time price in the West zone (Zone A) is actually down by almost 20% over the past year. Over the same period, the standard deviation in prices has increased by about 6%, so there has been a slight uptick in volatility. Moreover, similar trends can be observed in neighboring zones (B and C) that do not have major transmission constraints.

In the real-time energy market, the 12-month rolling average congestion component of the 5-minute real-time price in Zone A is up by more than 32% over the past year. Volatility has also increased as the standard deviation of congestion charges is up by more than 21% over that same time period. Congestion charges are also more than 20 times higher over the past year than in neighboring Zone C.

So it appears that NYISO’s system measures have so far confined the impact of mothballing Dunkirk and Huntley to higher pricing in the energy market. And while there appears to be no significant impact on the capacity and reserves market, the increased congestion and volatility reflected in energy pricing raises the likelihood of a capacity dispatch when the overall New York system becomes more constrained under hot weather conditions. Demand response customers in these western regions should be prepared for potentially more curtailment calls from NYISO than they’ve seen in previous summers.

To learn more about how to be better prepared for potential grid instability this summer in New York, contact Craig or any member of CPower’s New York Team.

Buildings Evolve. Your Building Management System Should, too.

July 13, 2016

In 1992, I co-authored a chapter for the second edition of the Energy Management Handbook titled “Energy Management Control Systems.” In it I described, among other ideas and practices, the importance of software to facilitate the ongoing success of an efficient energy management control system (EMCS).

We’ve seen a host of innovation in the energy industry during the 25 years since I originally published this chapter, but the principles I introduced remain sound.

Today the combination of automated building controls and up-to-date software can lead to an organization earning significant revenue through demand response participation. The key to optimizing demand response and maximizing your earnings comes down to maintaining your building management system so it can become an efficient tool for demand response.

Building usage and programming logic should evolve in lockstep.
Commercial building usage and environments continuously change throughout their lifetime. Activities, processes, schedules, space configuration and populations vary from time to time. When Building Management Systems (BMS) are first installed, the software programing logic (i.e. control sequencing, set points, etc.) is configured for building usage at that time.

It is essential that programming logic be kept current with any changes in a building’s use and environment. Failure to do so can result in control sequences and set points being over ridden, which negates the benefits envisioned by the intended energy management strategies.

Certain components of a building management system require regular maintenance.
Occupancy schedules need to be managed on a day-to-day basis at buildings that have sporadic after-hours occupancy, i.e. schedule a specific zone to be occupied for specific hours on a specific day. HVAC control sequences, set points, and zonal environmental control need to be periodically adjusted to adapt to changing usage and conditions.

Crucial components are often overlooked.
BMS maintenance agreements are a discretionary cost. These agreements typically focus on system hardware, which is perceived to be more impactful on the budget than software maintenance.

However, inefficient energy management can have a significantly greater impact on the budget. Vendors provide training for in-house staff on minimal software maintenance, such as—for example—changing set points and scheduling after-hours events, during initial installation.

This maintenance feature disappears when trained staff move on; however, changes to control sequencing require the use of vendor software engineers which require additional expenditures. Building staff are alert to hardware maintenance needs but tend not to recognize when software maintenance is needed.

A well-maintained building management system is advantageous for optimized demand response.
Demand response can be implemented with minimal disruption to building environmental conditions and usage when BMS programming logic is maintained current, whereas building conditions and usage in a building with a poorly maintained system can become uncomfortable causing disruption to building activity when responding to demand response events.

Demand response payments provide a source of funding for incorporating demand response sequencing and software maintenance in the BMS vendor’s ongoing maintenance agreement. CPower can advise on demand response control logic specific to each ISO.

Maintaining BMS software current not only ensures energy savings intended when the system was first installed but also provides a solid platform to reap substantial energy cost offsets afforded by participating in demand response. CPower can work with building managers to optimize the financial benefits that can accrue from participating in demand response by interfacing with the BMS to automate demand response event action and enhance performance with minimal impact on building environment.

Contact us and to find out if your building’s BMS is in need of an update, or to learn how you can earn revenue with demand response optimized through optimization.

Skip to content